Midland, TX New Home Permits: What to Expect Before Construction Begins

Home plans, a site plan, and a hard hat arranged on a construction desk beside a partially built house.

Building a new home involves more than choosing plans, materials, and finishes. Before construction starts, the project must pass through a permitting process designed to confirm that the proposed home meets zoning requirements, adopted building codes, and safety standards.

For residents planning new construction in Midland, understanding the sequence can help prevent avoidable delays, incomplete applications, and inspection problems.

What does a residential building permit cover?

A residential building permit authorizes construction of a new home after the city reviews the project for compliance with applicable requirements. A permit is generally required for new construction, additions, remodeling, repairs, and detached accessory buildings. ([midlandtexas.gov](https://midlandtexas.gov/1269/Building-Permits?utm_source=openai))

For a new home, the permit review commonly considers:

  • The site layout and required setbacks
  • The home’s size, design, and floor plan
  • Foundation and framing details
  • Electrical, plumbing, and mechanical systems
  • Energy-code documentation
  • Window and door information
  • The contractor listed for the project
  • Whether the property is properly platted and zoned for residential use

A building permit is not the same as approval for every separate activity. Electrical, plumbing, mechanical, irrigation, and utility-related work may involve additional applications or approvals.

What should be verified before submitting plans?

The property should be checked before the house plans are finalized. The city states that land proposed for construction must be platted and zoned for residential use. ([midlandtexas.gov](https://midlandtexas.gov/1269/Building-Permits?utm_source=openai))

This step matters because a home may face problems if the lot:

  • Has not been legally platted
  • Does not have residential zoning
  • Has setback limitations
  • Has easements affecting the buildable area
  • Requires access, drainage, or utility coordination
  • Is subject to conditions that affect lot coverage or placement

A site plan should show the proposed home in relation to property lines and required setbacks. In a growing community with varied lot sizes and newer subdivisions, the available building area may be narrower than the total lot size suggests.

It is also wise to confirm whether the property is inside the city’s permitting jurisdiction. Requirements can differ depending on whether land is within city limits or another jurisdiction.

What documents are typically required for a new home?

The city’s residential new-construction checklist identifies several core application items. These include the permit application, project valuation, square footage, contractor information, setbacks, and the applicable electrical, mechanical, and plumbing details. ([midlandtexas.gov](https://www.midlandtexas.gov/DocumentCenter/View/10327/Permit-Midland-CheckList?bidId=&utm_source=openai))

Plans and supporting documents may include:

  • Site plan with front, side, and rear setbacks
  • Floor plans and framing details
  • Foundation details showing dimensions and thickness
  • Exterior elevations
  • Window and door schedule
  • Energy-code documents
  • Manual J heating and cooling calculations, when required

Plans should agree with one another. For example, the square footage shown on the application should match the floor plans, and the foundation design should correspond with the structural layout. Inconsistent documents often result in review comments and resubmittals.

The city may request additional information at any stage. Submitting a complete, coordinated plan set is usually more efficient than sending partial information and correcting it later.

Who submits the permit application?

A property owner may be able to apply in some situations, but most new-home projects involve a licensed and bonded contractor registered with the city. The city’s checklist specifically instructs applicants to make sure a contractor is submitting the permit for residential new construction. ([midlandtexas.gov](https://www.midlandtexas.gov/DocumentCenter/View/10327/Permit-Midland-CheckList?bidId=&utm_source=openai))

The permit application identifies who is responsible for the construction work. That information should be accurate before submission because a contractor change may require an update to the permit record.

The city accepts digital permit submissions through PermitMidland. The online system allows users to apply for permits, upload documents, pay invoices, monitor application status, submit revisions, and schedule inspections. ([midlandtexas.gov](https://midlandtexas.gov/1424/PermitMidland?utm_source=openai))

How long does plan review take?

The city’s published permitting information states that residential plan review typically takes about five to seven business days, although the actual time can vary depending on project complexity, application completeness, review comments, and workload. ([midlandtexas.gov](https://midlandtexas.gov/1269/Building-Permits?utm_source=openai))

A typical sequence is:

1. Submit the application and required documents.
2. Pay the initial portion of the permit fee.
3. Wait for plan review.
4. Respond to correction comments, if any.
5. Receive approval and pay the remaining fee.
6. Obtain the permit number.
7. Post the permit where it is visible at the job site.

A review period is not a guaranteed construction start date. If plans require revisions, the project may go through another review cycle.

Custom Home Builder photo from Adobe Stock

Can construction begin while plans are still under review?

No. Construction should not begin until the permit has been issued and the approved plans are available as required. The city’s guidance states that the plan review must be complete and accepted, stamped plans must be on site before work begins. ([midlandtexas.gov](https://midlandtexas.gov/FAQ/Topic?mobile=ON&topic=17&utm_source=openai))
Starting early can create several problems:

  • Work may need to be removed or corrected.
  • Required inspections may be difficult to perform.
  • The project may lose its place in the inspection sequence.
  • Unapproved changes may require revised plans.
  • The permit may not cover work already completed.

This is particularly important for foundations, underground utilities, and concealed framing because inspectors need access to verify work before it is covered.

What inspections are required during construction?

Inspections occur at different stages rather than only after the home is complete. The city’s residential inspection material describes a workflow involving phase inspections and final inspections, with building, electrical, mechanical, and related inspection requests coordinated by permit number and property address. ([midlandtexas.gov](https://www.midlandtexas.gov/DocumentCenter/View/9689/Residential-Stages-of-Inspection?utm_source=openai))
Common inspection points may include:

  • Foundation or footing work
  • Underground plumbing and utilities
  • Slab or structural components
  • Framing
  • Electrical, mechanical, and plumbing rough-ins
  • Insulation and energy-related work
  • Final building inspection
  • Final trade inspections

The exact inspection schedule depends on the approved plans and project scope. Work generally should not be covered until the applicable inspection has been completed and approved.
Midland’s hot, dry conditions can make construction scheduling sensitive to soil moisture, excavation stability, concrete placement, and material storage. Weather may not eliminate a permit requirement, but it can affect when certain work is ready for inspection.

When can the home be occupied?

After the required work is complete and final inspections are approved, the city issues a Certificate of Occupancy for applicable new-construction projects. This document indicates that the building is approved for use or occupancy. ([midlandtexas.gov](https://midlandtexas.gov/201/Building-Permits-Inspections?utm_source=openai))
A house should not be treated as ready for occupancy simply because the interior appears finished. Unresolved trade inspections, missing documentation, incomplete safety items, or unapproved changes can delay final approval.

How long does a building permit remain valid?

The city states that construction must begin within 180 days after permit issuance and must not stop entirely for more than 180 days. If either period is exceeded, the permit may automatically expire and a new application may be required. ([midlandtexas.gov](https://midlandtexas.gov/1269/Building-Permits?utm_source=openai))
For that reason, permit records, inspection approvals, plan revisions, and contractor information should be kept organized throughout the project. The permit number is commonly needed when scheduling inspections, checking status, or communicating about corrections.

The adopted building-code list can change over time, and local amendments may apply. Before submitting a new-home application, applicants should verify the current requirements through Midland Development Services rather than relying on an older checklist or previously used plan set. ([midlandtexas.gov](https://midlandtexas.gov/1268/Building-Codes?utm_source=openai))

Chilton McKnight

About the Author

Chilton McKnight

Chilton McKnight joined his father in the home building business 5 years ago and played a role in founding Purple Key Homes. Prior to home building Chilton was a dedicated risk and insurance specialist working alongside real estate and construction companies across the US. This combined experience allows Purple Key Homes to deliver affordable excellence through craftsmanship and modern innovation, bringing the most quality home building and buying experience to Permian Basin communities.